Projects by School



Bellevue Elementary

Facility Improvement Measures

Start Date

Estimated Cost

Multipurpose Room Addition

October 2010

$1,371,900

Geo Project Elevated (Ventilation and Cooling)

Summer 2010

$1,738,878

Geo Project NON - Elevated

 

 

Drop Ceiling

Summer 2010

$358,300

Catwalk to H&V Units

Summer 2010

$71,200

Door Retrofit

Summer 2011

$68,700

Fire Sprinkler System

Summer 2010

$217,100

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

Summer 2010

$94,000

PC shutdown software

Summer 2011

$4,400

Plug Load Control

Summer 2011

$9,300

Freezer Temp Control

Summer 2011

$200

Sustainability Measures

Start Date

Estimated Cost

Solar Array

 

 

Water Fixture Retrofit

Summer 2011

$81,400

Solar Snow Melt

Summer 2011

$43,100

Irrigation Improvements

Summer 2011

$9,400

LEED-EB Documentation

Summer 2011

$14,400


Back to top


Carey Elementary School

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project Elevated (Ventilation and Cooling)

Summer 2010

$1,633,641

Geo Project NON - Elevated

 

 

Covered Walkway between buildings

Undetermined

$95,300

Door Retrofit

  November 2010

$68,700

Install Drop Ceiling

November 2010

$280,900

Repair Ductwork Insulation

November 2010

$3,600

Fire Sprinkler System

November 2010

$193,900

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

November 2010

$100,200

Waste Management System

November 2010

$69,100

PC Shutdown Software

November 2010

$3,100

Plug Load Control

November 2010

$5,300

Vending Miser

November 2010

$800

Window Retrofit

November 2010

$16,200

Sustainability Measures

Start Date

Estimated Cost

Irrigation Improvements

Undetermined

$72,300

Water Fixture Retrofit

November 2010

$65,300

Solar Array

 

 

LEED-EB Documentation

November 2010

$14,300


Carey Secondary School/Gymnasium

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project Elevated (Ventilation and Cooling)

November 2010

$2,314,703

Geo Project NON - Elevated

 

 

Catwalk to access Heating & Ventilation

November 2010

$71,200

Ground Source Heat Pump (Included in Geo project

  November 2010

 

HS Cooling Aid

November 2010

$17,800

Door Retrofit

November 2010

$20,600

Install Hot Water Circ Loop

November 2010

$10,300

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

November 2010

$59,500

Retro-Commissioning

November 2010

$45,400

PC Shutdown Software

November 2010

$3,300

Plug Load Control

November 2010

$5,300

Vending Miser

November 2010

$2,800

Domestic Hot Water set point adjustment

November 2010

$400

Sustainability Measures

Start Date

Estimated Cost

Water Fixture Retrofit

November 2010

$29,500

Solar Array

 

 

LEED-EB Documentation

November 2010

$28,400


Back to top


Community Campus Building

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project

January 2011

$1,725,294

Auditorium Improvements

Summer 2011

$882,500

Door Retrofit

January 2011  

$34,400

Install Drop Ceiling

January 2011

$615,900

Fire Sprinkler System

January 2011

$424,700

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

Summer 2011

$380,600

PC Shutdown Software

 

$800

Plug Load Control

 

$6,600

Install VFD on Heat Pump loop pumps

Summer 2011

$47,000

Retro-commissioning

Summer 2011

$56,300

Sustainability Measures

Start Date

Estimated Cost

Water Fixture Retrofit

January 2011

$54,500

Solar Array

 

 

LEED-EB Documentation

January 2011

$16,000


Back to top


District Office Building

Facility Improvement Measures

Start Date

Estimated Cost

HVAC Controls Retrofit

Undetermined

$31,300

Fire Sprinkler System

Undetermined

$43,800

Energy Conservation Measures

Start Date

Estimated Cost

PC Shutdown Software

Undetermined

$1,000

Plug Load Control

Undetermined

$4,500

Sustainability Measures

Start Date

Estimated Cost

LEED-EB Documentation

Undetermined

$14,300


Back to top


Hailey Elementary School

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project Elevated (Cooling)

Summer 2011

$3,495,650

Carpet/Flooring Replacement

Summer 2011

$279,000

Kitchen Remodel

Summer 2011

$289,400

Install Drop Ceiling

Summer 2011

$618,000

Door Retrofit

Summer 2011

$68,700

Transformer Move

Summer 2011

$109,900

Fire Sprinkler System

Summer 2011

$450,500

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

Summer 2011

$188,100

PC Shutdown Software

Summer 2011

$6,300

Plug Load Control

Summer 2011

$11,100

Vending Miser

Summer 2011

$1,400

Window Retrofit

Summer 2011

$23,700

Sustainability Measures

Start Date

Estimated Cost

Irrigation Improvement

Undetermined

$71,600

Solar Array

 

 

Water Fixture Retrofit

Summer 2011

$69,400

Solar Snow Melt

Undetermined

$43,100

LEED-EB Documentation

Summer 2011

$15,400


Back to top


Hemingway  Elementary School

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project Elevated (Ventilation and Cooling)

Summer 2012

$1,875,500

Geo Project NON - Elevated

 

 

Carpet Replacement

Summer 2012

$305,600

Solution to East Side of Building (ice)

Summer 2012

$143,200

Door Retrofit

Summer 2012

$96,200

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

Summer 2012

$138,300

PC Shutdown Software

Summer 2012

$7,800

Plug Load Control

Summer 2012

$8,500

Vending Miser

Summer 2012

$800

Sustainability Measures

Start Date

Estimated Cost

Day Lighting

Summer 2012

$199,600

Water Fixture Retrofit

Summer 2012

$40,400

Solar Array

 

 

LEED-EB Documentation

Summer 2012

$14,500


Back to top

Silver Creek High School

Facility Improvement Measures

Start Date

Estimated Cost

HVAC Retrofit

 

 

HVAC Controls Retrofit

 

 

Fire Sprinkler System

 

 

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

 

 

PC Shutdown Software

 

 

Plug Load Control

 

 

Sustainability Measures

Start Date

Estimated Cost

LEED-EB Documentation

 

 


Back to top

District Support Services Building

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project

January 2011

 $501,224

HVAC Retrofit

January 2011

$20,600

Ground Source Heat Pump (Included in Geo Project)

 

 

Security Upgrades

 

 

Data Center

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

January 2011

$59,300

PC Shutdown Software

January 2011

$1,500

Plug Load Control

January 2011

$13,200

Waste Oil Furnace

January 2011

$10,800

Retro-Commissioning

January 2011

$37,700

Sustainability Measures

Start Date

Estimated Cost

Water Fixture Retrofit

January 2011

$16,300

Solar Array

 

LEED-EB Documentation

January 2011

 $14,300


Back to top

Wood River High School

Energy Conservation Measures

Start Date

Estimated Cost

Geo Project

January 2011

$1,250,000

Lighting and Occ Sensors

January 2011

$104,400

PC Shutdown Software

January 2011

$15,600

Plug Load Control

January 2011

$19,200

Install VFD on HP loop pumps

January 2011

$113,400

Retro-Commissioning

January 2011

$120,500

Ground Source Heat Pump (include in Geo Project)

Sustainability Measures

Start Date

Estimated Cost

Irrigation Improvements

$82,900

Solar Array

 

Solar Snow Melt

Undetermined

$43,100

Heat Recovery for Domestic Water

January 2011

$49,900

LEED-EB Documentation

January 2011

 $18,100


Back to top

Wood River Middle School

Facility Improvement Measures

Start Date

Estimated Cost

Geo Project

 

$2,893,376

Security Upgrades

 

 

Energy Conservation Measures

Start Date

Estimated Cost

Lighting and Occ Sensors

Undetermined

$59,100

PC Shutdown Software

Undetermined

$12,900

Plug Load Control

Undetermined

$16,100

Install VFD on HP loop pumps

Undetermined

$76,300

Retro-Commission

Undetermined

$81,000

Waste Management System

Undetermined

$69,100

Sustainability Measures

Start Date

Estimated Cost

Solar Array - Pilot

Undetermined

$234,600

LEED-EB Documentation

Undetermined

 $17,300


Back to top

Woodside Elementary School

Energy Conservation Measures

Start Date

Estimated Cost

Geo Project-Woodside

$1,096,908

Lighting and Occ Sensors

Undetermined

$53,300

PC Shutdown Software

Undetermined

$4,500

Plug Load Control

Undetermined

$11,900

Install VFD on HP loop pumps

Undetermined

$74,300

Retro-Commission

Undetermined

$66,400

Sustainability Measures

Start Date

Estimated Cost

Irrigation Improvements

$30,700

Solar Array

 

LEED-EB Documentation

 

 $14,500


Back to top

Wood River High School/Community Campus/DSS Building

Facility Improvement Measures

Start Date

Estimated Cost

Geo Wells for Campus

November 2011

$2,500,849

Waste Management System

January 2011

$69,100


Back to top